2011 - 2012General inspection daily to different machines.
Preparation of preventive maintenance: work permit, work order; according to the
maintenance program. (PM= Plant+ frequency+ work specification (W spec))
Use the « ENGICA » GMAO.
Follow the Dashboard using KPI « ENGICA ».
Control room: leading a night/day shift team in the operation of the combined cycle Power Plant.
Maintenance of fire fighting system (ionic and thermostatic fire detectors, gas detectors…..) as well as the gas monitoring system.
Preventive and curative maintenance of all kinds of instruments (checking and calibration Of positioners, Transmitter’s pressure, thermo and level switches, indicators,thermocouples, analyzers :( Emerson, Honeywell, ABB, Siemens, Orion, ROTORK,TARTARINI…..).
Intervention types: repair and replacement of all failing parts
(Bearings, mechanical seal, clutch, coupling…alignment).
Electrical Power & Quality Analyser CHAUVIN ARNOUX QualiSTAR C.A 8334.